Chip surveyed the courtyard for grade, then fill had to be removed, and
compacted.
Next steel was installed and Art put in the plumbing for the drain.
Since the courtyard was constrained by walls on most of its sides, we
poured it in three sections.
Before we poured the middle section, Clada and Edward poured a
retaining wall.
This gave the concrete time
to start setting up for floating before the middle section was
poured. Gus has long arms!
Joseph
bullfloated from a number of different angles.
Clada is happy that concrete
pours are getting fewer and fewer...